Pink Line

The route alignment

         

            The route starts on Rattanathibet Road at the Nonthaburi Civic Center, which is an interchange with the MRT Purple Line (Bang Yai - Tao Poon section) at Nonthaburi Civic Center Station. The route then turns left at Khae Rai Intersection onto Tiwanon Road and continues to Pak Kret Intersection, where it turns right to follow Chaeng Watthana Road. It passes Muang Thong Thani, the Chaeng Watthana Government Complex, goes under the Uttraphimuk Elevated Highway (Don Mueang Tollway), and passes in front of Phranakhon Rajabhat University and the Constitution Protection Monument Roundabout. From there, the route runs along Ram Inthra Road to Min Buri Intersection, then follows Sihaburanukit Road. It crosses Khlong Sam Wa, turns right to cross Khlong Saen Saep and Ramkhamhaeng Road (Sukhaphiban 3), and ends at the area near the intersection of Ramkhamhaeng and Rom Klao Roads at Min Buri Station, which is a connection point with the MRT Orange Line project.


Basic Information


Structure                    :         Elevated structure entire route

Systems                     :         Straddle Monorail

                                         (Maximum capacity : 28,000 passengers per hour per direction)

Distance                     :         34.5 km.

Station                        :        30 Stations

Investment scheme       :        PPP Net Cost

                                         (The private sector is responsible for investing in Construction cost, M&E, rolling stock and O&M while the public sector subsidy construction cost)

Concession period       :         30 years

Concessionaire            :         Northern Bangkok Monorail Company Limited (NBM) (Concession Agreement signed on 16 June 2017)


Depot and Park&Ride Building

            -   The Depot is located at Min Buri Station.

            -   The Park&Ride Building is located at Min Buri Station. (capacity : 3,000 vehicles)

            * Ref: Concession Agreement for the MRT Pink Line Project (Khae Rai - Min Buri Section), dated 16 June 2017 

Benefits of Project


      -         Economic Internal Rate of Return (EIRR) = 17.20%*

      -         Financial Internal Rate of Return (FIRR) = 5.43%*

      -         Ridership Forecast on the service launching date = 199,054 passenger - trips/day**

      * Ref. PPP Report of The MRT Pink Line (Khae Rai - Min Buri) as of July 2015

      ** Ref. The concession contract for The MRT Pink Line on 16 June 2017

Project Implementation


Construction Commencement

:

June 29, 2018

Service Launching Date

:

December 31, 2023

Service Information


         -         Operating Time : 06.00 - 24.00 น. (Daily)

         -         Tickets Information : -

         -         Fare rate : -

         -         Average Daily Passenger : -

         -         Parking Service : -

         -         News/Special Event : -