Phuket International Airport

The route alignment


            The route starts at Phuket International Airport, with the initial section being an elevated structure along Highway No. 4031. Then descends to ground level at Highway No. 4026, before elevating again to cross the airport junction and underpass. After making a right turn, the route returns to ground level along Highway No. 402 to enter Phuket City. The alignment transitions into an underground tunnel for approximately 3 kilometers at Thalang District area. Then re-emerges at ground level, passing the Heroines’ Monument (Thao Thep Krasattri – Thao Si Sunthon Monument). Before reaching the Bang Ku Junction, the route descends underground again to pass beneath the junction, and then rises back to ground level. It continues past the bus terminal into the Phuket Municipality area via Phuket Road, crossing the Thep Srisin Bridge (over the Ko Phi Canal) to enter Chao Fa East Road (Highway No. 4021), and finally terminates at the Chalong Five-Way Intersection.

Basic Information


Structure : Elevated/ Ground level/ Underground structure

Systems : LRT / Tramway (Light Rail Transit/Low Floor Tram)

Distance : 42.0 km. 

Station         : 21 Stations (1 Elevated Stations / 1 Underground Stations / 19 Ground Stations)  


Depot and Park&Ride Building

        - The Depot is located along Highway No. 402 (Inbound side) near Tesco Lotus’s (Thalang branch)

        - The Park&Ride Building are located at Phuket Bus Terminal 2 and Chalong Station.


Benefits of Project


      -    Economic Internal Rate of Return (EIRR) = 13.11%

      -    Financial Internal Rate of Return (FIRR) = 2.34%

      -    Ridership Forecast on the service launching date = 39,000 passenger - trips/day

           * Ref. PPP Report of Phuket Mass Transit System as of October 2020 (Executive summary report)

Project Implementation Plan


Cabinet Approval for Construction

:

February 2027

Scheduled to start Construction

:

September 2028

Expected to operate

:

December 2031

           * MRTA project Implementation plan acknowledged by the MRTA Board of Directors on Jul 14, 2025

Current Status


           -      In the process of reviewing the feasibility study and preparing the PPP report in order to MOT's assignment, which will be waiting for the completion of the Highway No. 4027 Project for serving as a bypass, before implementing the Phuket Mass Transit project.

           -      Other Public Information : (ประสานส่วนงานที่เกี่ยวข้องเพื่อเชื่อมต่อข้อมูล)