Project Cost

17 October 2565
Detail
Cost
Unit
Land Acquisition
1,746.25
million baht
Civil works
10,337.78
million baht
Track works
1,633.55
million baht
M&E Works
4,430.42
million baht
Rolling Stocks
2,645.00
million baht
Consultant Fee
686.17
million baht
Overhead & Profit
1,578.63
million baht
Tax
1,491.80
million baht
Total
24,549.00
million baht

Source

        Project Feasibility Study Report Bangkok Mass Transit System Bearing – Samutprakan Section from Office of Transport and Traffic Policy and Planning (December, 2007)