Background
17 October 2565 According to the Cabinet’s meeting on November 7, 2006, the Cabinet has approved in principle for Mass Transit System Development Project in Bangkok and suburban area as the Ministry of Transport proposed. The Project has proposed 4 high priority projects comprising of 5 lines. For the Green Line Project section: On Nut – Bearing – Samut Prakan, the Bangkok Metropolitan Administration (BMA) has proceeded in civil work construction in On Nut – Bearing section for 5.25 kilometers length. The portion Bearing – Samrong – Samut Prakan is in an area which is responsible by Samut Prakan province. However, BMA has also preceded a study of the mass transit system extension development project and carried out a preliminary design drawing of the extension from Bearing – Samrong – Samut Prakan and Mo Chit – Kaset – Saphanmai section.