TBM2 breaks through Ramkhamhaeng 12 Station

          Mass Rapid Transit Authority of Thailand and a contractor of Contract 1: underground civil works of the MRT Orange Line Project: Thailand Cultural Centre Min Buri (Suwinthawong) Section, CKST Joint Venture announced that the Tunnel Boring Machine 2, Burapha Choke (TBM2), launching from MRTA Station on July 15, 2020, recently broke through into Ramkhamhaeng 12 Station site. The TBM2 is driving to the next station, Ramkhamhaeng Station and is scheduled to break through into the station in January 2020. Presently, the overall civil works progress of the MRT Orange Line Project as at the end of September is 69.82%.