Phitsanulok Mass Transit Project (Red Line)

Website

         -

Brochure

         -

Video

         -

Background

     Phitsanulok Mass Transit System Project (Red Line: Phisanulok University - Central Plaza Section) is one of the transportation system development projects linking main cities in the provincial areas and solving traffic problems from main cities in the provincial areas to Bangkok metropolitan area. The project objects to provide continuous, convenience and safe travel according to the Strategic development of transport infrastructure of Thailand 2015 to 2022 which assigns Office of Transport and Traffic Policy and Planning to feasibility study and preliminary design of Phitsanulok Transit System. The project is divided into 2 phases. The first phase is consisted of 6 routes of 80.5 km. and the second phase is consisted of 2 extension routes and 2 new routes of 30.1 km. The result of the feasibility study recommends to operate the first phase Red Line: Phisanulok University - Central Plaza Section which is the appropriate routes to operate first and the cabinet resolution has already assigned MRTA to implement the project.

Characteristics

Alignment

     It starts from Phitsanulok University passing Phitsanulok Bus Terminal 2 heading to the north along Highway 126 to meet Highway 12 at Indochina intersection. Then, it goes to the west along Highway 12 and ends at Phitsanulok Central Department Store. It passes several landmarks such as Makro Department Store, Tesco Lotus, Chinnalap Village, Phitsanulok Bus Terminal 1, Phitsanulok Technical Commercial School, Topland Department Store, Wat Phra Sri Rattana Mahathat, Phitsanulok Provincial Hall, Wat Khuha Sawan and Phitsanulok Mueang Mai Village.

Structure+

     At-grade track and total length of 12.6 km.

System

     Auto Tram System (Rubber-tire tram)

Station

     The project consists of 15 stations.

Depot

     There is 1 depot at Phitsanulok University which is functioned as depot, train park and office.

Park and Ride

     There are 2 park and ride areas; Phitsanulok University Park and Ride and the area opposite Phitsanulok Central Department Store.

Project Cost

Detail Cost (Million baht)
Land Acquisition 235.55
Civil works 162.29
M&E Works and Rolling Stocks 1,073.69
Consultant Fee 75.23
Other expense (Pre-operated expense) 20.00
Total 1,566.76

Source

     Feasibility Study and Preliminary Design of Phitsanulok Transit System (Final Report) by OTP, November 2018