PROGRESS OF WORK |
| |
1. Pre-construction
Activities
Preliminary Engineering Design
Preliminary engineering design of the ISP project has been
completed since mid of 1996. The design of the south section,
Hua Lumphong - Huai Kwang, was made by a group of consultants
led by Halcrow Asia, whereas the north section was by Dorsch Consult.
Selection of Consultants
(1) Project Management Consultant (PMC)
The MRTA has engaged a group of consultants led by De Luew
Cather International Inc. to act as their Project Management
Consultant (PMC) with a cost of 947 million baht. PMC will perform
various duties, including inspection of engineering design,
control of the overall project schedule, and coordination among
contractors and concessionaire, etc. Their work will not be
complete until a successful commercial operation of the system.
(2) Construction Supervision Consultants (CSC1 & CSC2)
The MRTA has engaged a group of consultants led by Louis
Burger International, Inc. to be their Construction Supervision
Consultant (CSC 1) with an approximate cost of 1,113 million
baht for supervising the construction of civil work contracts
I, II and Vand to be Front End Design Consultant (FEDC) with
an approximate cost of 50 million baht for providing the preliminary
system-wide M&E design interface required for all the designated
contractors.
(3) M&E Supervision Consultant (MESC)
The MRTA has engaged a group of consultants led by Electrowatt
Engineering (Thailand) to supervise the installation of the
M&E works of the concessionaire, with a cost of 480 million
baht.
Selection of Civil Work Contractors
(1) Contract I : Underground Structure - South
The MRTA has appointed the Joint Venture BCKT to design and
construct the underground structures-south. The contract was
signed on November 17, 1996 with the cost of 23,900 million
baht (VAT excluded). According to the contract, the contractor
has to complete the work within five years.
(2) Contract II : Underground Structure-North
The MRTA has engaged the Joint Venture ION to design and construct
the underground structures-north with the cost of 28,500 million
baht (VAT excluded) on July 10, 1997. Like Contract I, the contractor
has to complete the work within five years.
(3) Contract III : Depot
The contract has signed with Siam/Nippon Metro Consortium
on November 24, 1998. This 6,329 million baht contract (VAT
excluded) has to complete within three years.
(4) Contract IV : Trackwork
The contract has been signed with Joint Venture CKSL on October
15, 1999 with the contract amount of 3,019.5 million baht (VAT
excluded). The contract will be fully completed within mid of
2003.
(5) Contract V : Lifts and Escalators
The MRTA has engaged the MMW Joint Venture with the cost of
1,810 million baht (VAT excluded) on November 12, 1998. The
contract will be fullly completed within mid of 2003.
Selection of M&E Works and Operation Concession
MRTA has signed the concession contract with the Bangkok Metro
Company Limited (BMCL) on August 1, 2000.
|
|
2. Process of Works
- Up to the end of May 2002, the actual overall progress of works
is estimated at 95.74 against 95.95% planned.
|